Case Study – Notcutts Rivendell, Widnes

187.86 kWp Commercial Rooftop Solar PV Installation 

Project Overview

    • Client: Notcutts Ltd
    • Location: Notcutts Rivendell, Mill Lane, Widnes, Cheshire
    • System Size: 187.86 kWp
    • Panels: 404 × Solar Panels
    • Inverters: 7 × Solis Inverters
    • Completed: October 2026
    • Estimated Carbon Savings: ~27.78 tonnes of CO₂ per year

The Background

We have worked with Notcutts for over 12 years to roll out commercial solar across their UK garden centres, helping them cut energy bills and move away from gas toward electric operations. Following projects at Woodbridge, Oxford, and Ditchling, our team was asked to design and install a rooftop system at Notcutts Rivendell in Widnes.  Garden centres are a great match for solar power. Between the kitchen, retail lighting, and climate-controlled areas, most of their electricity is used during daylight hours. That means the power generated on the roof gets used straight away on site rather than going back to the grid.

The Solution

In October 2026, our engineers worked alongside local electrical contractors SWS Northwest Ltd to install a 187.86 kWp array across the main shop roof.  We fitted 404 465W panels connected to seven Solis inverters, laid out to suit the different roof sections. To satisfy local grid requirements, we also installed a G100 export limitation system, total generation meters, and remote monitoring so Notcutts can keep track of how the system is performing alongside their other sites.

The Results

The installation was completed and commissioned in three weeks. The system now generates clean electricity directly for the Widnes store, cutting reliance on the grid and saving around 28 tonnes of CO₂ every year.

With Rivendell up and running, our commercial team is continuing the rollout with Notcutts, with St Albans and Solihull next on the list.